H6&H8 1F slab & beam steel fixing-shing (1)
|
| H1&H3 PF-1F wallform erect-shing
|
| H6&H8 1F slab & beam steel fixing-shing
|
| T8 dismantle bamboo scaffloding-shing
|
|
|
|
|
|
|
T8 57F glass parapet install-shing
|
| T8 main roof stone cladding-shing
|
| T7 50F Dismantle of TRC [Chi]
|
| T6 RF Application of waterproofing membrane [Chi]
|
|
|
|
|
|
|
T6 RF Cleaning work [Chi]
|
| T6 RF Erection of materials hoist [Chi]
|
| T5 - 56F pipe duct skirting [Hang]
|
| T5 - 11F refuse room wall tiling [Hang]
|
|