Podium Floor L3(Garage Area)-Wall&Column Lime Plastering[HO]
|
| Podium Floor L2(Garage Access Road)-Floor Cleaning General View[HO]
|
| Podium Floor 3(Switch Room)-Wall Bricklaying[HO]
|
| Podium Floor L5(TBE Plant Room)-Wall Bricklaying[HO]
|
|
|
|
|
|
|
Elec. cable wiring at Flat 22 33F T3 [Leo]
|
| Exhaust air ductworks at 50F of T3 [Leo]
|
| H1 2F slab concreting-shing
|
| H3 2F-roof wall steel fixing-shing
|
|
|
|
|
|
|
Podium _ setting out works at soffit fwk of outdoor swimming pool[wai]
|
| Podium _ steel fixing to GF beam at deferred portion of Podium Floor[wai]
|
| Reinstatement works at external area along Lok Man Sun Chuen[wai]
|
| T3 - 52F ext. water pipe painting [Hang]
|
|