Rebar fixing for slab at GL 1-2,A-PC of M2F(1)
|
| Rebar fixing for wall WP2 at M3F-GF
|
| Rebar fixing for slab at GL 1-2,A-PC of M2F(3)
|
| Rebar fixing for slab at GL 7-9,PB-PC of M3F
|
|
|
|
|
|
Rebar fixing for starter bars & making good of beam rebar at GL 1-2,A-PC of M2F
|
| Rebar fixing for wall WP1 at GL 1-7,A of M3F-GF
|
| Soil test for GL 10-11,PA-PB of LGF(3)
|
| Rebar fixing of starter bars to slab at GL 1-2,A-PC of M2F
|
|
|
|
|
|
Remedial work for water supply by Water Supplies Department contractor at outside the site
|
| Soil test for GL 10-11,PA-PB of LGF(1)
|
| Soil test for GL 10-11,PA-PB of LGF(2)
|
| Wrong Voltex & Miradrain fixing between GL 1,PC of M2F slab
|
|