KSR Site Overview on 10-8-12
|
| Closing fwk for screen wall at GL1,A-PC of M2F-M3F
|
| Bottom slab of 100mm gap fixing at Flushing water tank of M3F(1)
|
| Bottom slab of 100mm gap fixing at Flushing water tank of M3F(2)
|
|
|
|
|
|
|
Closing fwk for screen wall at GL1,A of M2F-M3F
|
| | Concreting for slab & beam at GL 3-9,PB-PD of M3F(1)
|
| Concreting for slab & beam at GL 3-9,PB-PD of M3F(2)
|
|
|
|
|
|
|
| | Joint filler fixing between FS Sprinkler tank & 100mm wall at M2F-M3F(3)
|
| |