KSR Site Overview on 14-8-12 0800 a.m.
|
| KSR Site Overview on 14-8-12 1800 p.m.
|
| CJ fixing for matreial hoist area at GL 1-2,PA-PB of M3F
|
| Before close fwk of wall at GL 9,PA of M3F-GF
|
|
|
|
|
|
CJ fixing for ELS strut at GL 1-2,PD-Q of M3F
|
| Closing fwk for wall WP7 at M3F-GF
|
| Closing fwk for Fan room wall at GL 9,PA of M3F-GF
|
| Closing fwk for wall WP1 at M3F-GF
|
|
|
|
|
|
Closing fwk for wall WP2 at M3F-GF
|
| Concrete surrounding for manhole FMH-03 & STG of drainage pipes at GL 10-11,PB-PC of LGF(4)
|
| Concrete surrounding for manhole FMH-03 & STG of drainage pipes at GL 10-11,PB-PC of LGF(1)
|
| Concrete surrounding for manhole FMH-03 & STG of drainage pipes at GL 10-11,PB-PC of LGF(2)
|
|