Concrete surrounding for drainage pipes from TG to SMH-10 & SMH-11 & FMH-01 of LGF(3)
Concrete surrounding for drainage pipes from TG to SMH-10 & SMH-11 & FMH-01 of LGF(4)
General view at M3F
Erecting falsework for fwk to soffit slab & beam at GL 1-3,PD-Q from M3F to GF
Concrete surrounding for drainage pipes from TG to SMH-10 & SMH-11 & FMH-01 of LGF(3)
Concrete surrounding for drainage pipes from TG to SMH-10 & SMH-11 & FMH-01 of LGF(4)
General view at M3F
Erecting falsework for fwk to soffit slab & beam at GL 1-3,PD-Q from M3F to GF
Erecting falsework for fwk to soffit slab & beam at GL 1-5,PC-PD from M3F to GF
Erecting falsework for fwk to soffit slab & beam at GL 1-9,PD-Q from M3F to GF
General view at GL 10-11,A-Q of LGF
Inside of Lift pit no.1 at M3F-GF
Erecting falsework for fwk to soffit slab & beam at GL 1-5,PC-PD from M3F to GF
Erecting falsework for fwk to soffit slab & beam at GL 1-9,PD-Q from M3F to GF
General view at GL 10-11,A-Q of LGF
Inside of Lift pit no.1 at M3F-GF
Lift pit no.5 & 6 at LGF
Outside of Lift pit no.1 at M3F-GF
Rebar fxing for wall & bottom slab at Potable Water Tank of M3F
Welding test for alum. cladding of embed at LGF
Lift pit no.5 & 6 at LGF
Outside of Lift pit no.1 at M3F-GF
Rebar fxing for wall & bottom slab at Potable Water Tank of M3F
Welding test for alum. cladding of embed at LGF