ksr007 :: 200712
Last changed: Jul 20, 2012
19 items in this album
KSR Site Overview on 20-7-12
Fwk for wall WP2 at M2F-M3F
Backfilling soil at M1F
Concealed puddle flange at Sprinkler tank of M2F
KSR Site Overview on 20-7-12
Fwk for wall WP2 at M2F-M3F
Backfilling soil at M1F
Concealed puddle flange at Sprinkler tank of M2F
Cutting the ELS stud at GL 1,PD of M1F
Filling soil from GF to M1F
Open up the conc. for drill in rebar holes at GL 10,PB of LGF
GL 10-11,PA-Q of LGF
Cutting the ELS stud at GL 1,PD of M1F
Filling soil from GF to M1F
Open up the conc. for drill in rebar holes at GL 10,PB of LGF
GL 10-11,PA-Q of LGF
Installation of cooling pipes at col.CP34 of M2F-M3F
Joint filler fixing for 50mm gap at between wall WP6 & Sprinkler tank of M2F(1)
Joint filler fixing for 50mm gap at between wall WP6 & Sprinkler tank of M2F(2)
Voltex & Miradrain9000 at GL 7-9,PB-PC of M1F(1)
Installation of cooling pipes at col.CP34 of M2F-M3F
Joint filler fixing for 50mm gap at between wall WP6 & Sprinkler tank of M2F(1)
Joint filler fixing for 50mm gap at between wall WP6 & Sprinkler tank of M2F(2)
Voltex & Miradrain9000 at GL 7-9,PB-PC of M1F(1)