KSR Site Overview on 20-8-12
Blinding layer at GL 10-11,PC-Q of LGF
After concreting at Potable Water Tank of M3F
After concreting to slab at GL 10-11,A-PC of LGF
KSR Site Overview on 20-8-12
Blinding layer at GL 10-11,PC-Q of LGF
After concreting at Potable Water Tank of M3F
After concreting to slab at GL 10-11,A-PC of LGF
Before concreting for 225mm STG at GL 11,PD of LGF
Before concreting for 100mm STG at GL 11,PD of LGF
Bamboo scaffolding at GL 7-9,A-PA of GF ext. wall
Closing fwk for col. CP33 & P.D. at M3F-GF
Before concreting for 225mm STG at GL 11,PD of LGF
Before concreting for 100mm STG at GL 11,PD of LGF
Bamboo scaffolding at GL 7-9,A-PA of GF ext. wall
Closing fwk for col. CP33 & P.D. at M3F-GF
Closing fwk for wall at GL 1-2,A of M3F-GF
Closing fwk for wall at GL 2-3,PA-PB of M3F-GF
Closing fwk for wall at lift pit no. 5 & 6 of LGF(1)
Closing fwk for wall at lift pit no. 5 & 6 of LGF(2)
Closing fwk for wall at GL 1-2,A of M3F-GF
Closing fwk for wall at GL 2-3,PA-PB of M3F-GF
Closing fwk for wall at lift pit no. 5 & 6 of LGF(1)
Closing fwk for wall at lift pit no. 5 & 6 of LGF(2)