| Fwk to soffit beam & slab at GL 7-9,PB-Q of M2F(1)
|
| Cutting off the I bars at GL 1-2,PD-Q of M2F-M3F(1)
|
| Cutting off the I bars at GL 1-2,PD-Q of M2F-M3F(2)
|
|
|
|
|
|
|
Cutting off the I bars at GL 1-2,PD-Q of M2F-M3F(3)
|
| Fwk to manholes wall & bottom slab at manholes FMH-02a & FMH-04 of LGF
|
| Rebar fixing for beam at GL 7,PD-Q of M2F
|
| Fwk to soffit beam & slab at GL 7-9,PB-Q of M2F(2)
|
|
|
|
|
|
|
General view at GL 10-11,PB-Q of LGF
|
| Making good for bamboo scafffolding at GL 7,A-PB of M1F-M2F(1)
|
| Making good for bamboo scafffolding at GL 7,A-PB of M1F-M2F(2)
|