KSR Site Overview on 30-7-12
|
| | | |
|
|
|
|
Concreting for slab & beam at GL 1-7,PD-Q of M2F-M3F ramp
|
| Beam no. M2B26 80mm sleeve (100mm sleeve for M2F CBWD, 65mm sleeve for M1F CBWD)
|
| C.J. fixing at GL 9,PB-Q of M2F
|
| Closing fwk for col. CP23 at M2F-M3F
|
|
|
|
|
|
Concreting & Floor rendering for slab & beam at GL 7-9,PB-Q of M2F(2)
|
| Cutting off the strut at GL 1,A-PB of M2F-M3F
|
| Concreting for slab & beam at GL 7-9,PB-Q of M2F(1)
|
| Concreting for tie beam at GL 10-11,A-PA of LGF(1)
|
|